Any accident foreseen in this frame?
|
At a construction site of burying city water pipes, a hydraulic excavator is traveling with a pipe weighing 53 kg that is hung with a wire rope fixed at the center. A worker is holding the pipe with his hand to prevent it from swaying. Now what accident do you foresee occurring in this frame?
|
 |
This is the accident resulted!
|
The operator suddenly changed the course to avoid a big stone ahead. Then the hung pipe made a big sway, pulling the worker down. He was run over by the excavator and killed.
|

|
Tips for forestalling similar accidents
|
1. |
Strictly follow the rules restricting the use of hydraulic excavators in unintended applications (see the Article 164 of Rules of Industrial Safety and Health Law).
|
2. |
Take every precaution for safety at the worksite beforehand. In this instance remove, remove big stones lying on the planned traveling course.
|
3. |
Train operators thoroughly not to jerk hydraulic excavators as well as their work equipment.
|